Medical Pavilion, CD Surge
Back to Case Studies

Overflow Construction Document Production

Medical Pavilion, CD Surge

Seven weeks from a fixed permit deadline, the client lost its job captain and was left short of the detailing and notes still needed on a 0 SF medical pavilion. NorthRoom took the remaining construction-document scope, including plans, sections, details, and schedules, produced it in the client's Revit template, and checked it against the client's internal QA standards.

Engagement Data

Client0-person multi discipline architecture firm
LocationNew England
EngagementProject-Based
Duration0 Weeks
Team Size0 Production Staff
ToolsRevit, AutoCAD

Client identity is confidential, per our anonymity policy, we never disclose which firms use production support.

Discuss a Similar Engagement

The Result

0

Sheets Produced

0 wks

Start to Permit

0

Permit Comments on Our Scope

The Situation

The permit date was fixed by the state review cycle. Hiring was too slow, overtime alone wouldn't close a gap of that size, and the firm refused to submit documents that didn't meet its own reputation for quality.

Our Approach

We embedded a four-person production team in the client's standards during a two-day alignment phase, then ran weekly production sprints with daily status updates. Every batch passed through both our QA checklist and the client's internal review before integration into the master set.